Progress Report of JNNURM Work as on 29 May 2010

 

 

Current Work Photograph

(Water Supply & Sewerage)

Work Progress Report (Progress of work done upto date)  
NAD-008 & 012                   Date : 30-05-2010  
Work Progress Report 
Sr. No. Name of work/ Package No. Name of Contractor Date award / Comm date Award Cost (Rs. In Lakhs)  Total Length (km) Description Cumm. Progress upto Last Week  (km) Length completed During this week (km) Cumm. Progress up-to-date (km) Balance to be completed (km) Cumm. Value of work (Rs in Lakhs)  % Physical progress % Financial Progress 
1 Package I M/s. M.T. Phad 22-Dec-06 3517 222 Completed As per DPR 3500 100.00% 99.53%
Transmission and Distribution system North
2 Package II M/s. NCC Ltd. 22-Dec-06 2492 103 Completed As per DPR 2474 100.00% 99.26%
Transmission and Distribution system South

 

Work Progress Report (Progress of work done upto date)  
NAD009,010,011                   Date : 30-05-2010  
 Sewerage Collection 
Sr. No. Name of work Name of Contractor Date award / Comm date Award Cost (Rs. In Lakhs)  Total Length (km) Description Cumm. Progress upto Last Week  (km) Length completed During this week (km) Cumm. Progress up-to-date (km) Balance to be completed . Length (km) Cumm. Value of work (Rs in Lakhs) % Physical Progress % Financial Progress
1 Sewerage North M/s Indu Project Ltd. 16-Apr-07 7450.245 208.89 Supply 83.456 9.000 92.456 116.434 2071 44.26% 27.80%
Laying 70.530 0.700 71.230 137.660 34.10%
2 Sewerage South M/s Sharda Construction Company Nanded. 26-Apr-07 2611 48.607 Completed as per DPR 2138 100.00% 81.88%

 

  (Roads)

Weekly Progress Report for Road Works
(For the week ending on 29 th May 2010) 
Sr. No. Road No. / Length (mtr) Name of Road Name of Contractor Date of Award % Cummulative progress  Scheduled / Expected Completion
1 2 3 4 5 6 7
NAD-006          
Package-IIIA
1 1/675 Railway station to Gurudwara gate no 1 R.K. Madhani & Co.  July – 07 50.49 July-08
--------------      Dec-10
2 2/540 Vazirabad Police station to Gurudwara Gate no. 1 R.K. Madhani & Co.  Jul-07 100.00 Completed
3 Text Box: 3B
Text Box: 3A
3/760
Gurudwara Gate No. 1  Bhagat Singh Road R.K. Madhani & Co.  Jul-07 100.00 Completed
Bhagat Singh Road to  Keli Market R.K. Madhani & Co.  Jul-07 82.00 July-08
--------------
June-10
             
Package-IVB
4 Text Box: 7A
Text Box: 7C
Text Box: 7B
7/2990
Regional Workshop to PanchSheel Dresses M/s B.C.Biyani Jun-08 100.00 Completed
Panchsheel Dresses to ITI M/s B.C.Biyani Jun-08 100.00 Completed
1).ITI to Shivaji Nagar ROB M/s K.T.Construction Feb-09 100.00 Completed
2).Kalamandir to Muth Chowk 95.00 May-08
--------------
June-10
5 8 / 3050 Mutha Chowk to Mahaveer Chowk  M/s K.T.Construction Jul-07 100.00 Completed
Mahaveer Chowk to  Tower  M/s Rajdeep Buildcon Jul-07 47.00 July-08
--------------
After Completion of Sewerage Work
Tower to Barki Chowk  M/s S.Kumar Construction Aug-09 49.00 Feb-10
--------------     Aug-10
 Barki Chowk to Degloor Naka M/s R.M.Hendre Oct-08 Substantially Completed April-09
--------------
May-10
             
NAD-014          
Package-IA
1 30 / 1538 Latur Road to Milk Diary Rajdeep Buildcon Pvt. Ltd.  May – 07 100.00 Completed
2 31 / 944 Navghat bridge to Milk diary Rajdeep Buildcon Pvt. Ltd.  May – 07 100.00 Completed
3 34/2052 Rest House to Pawdewadi Naka Rajdeep Buildcon Pvt. Ltd.  May – 07 100.00 Completed
4 38-A/3154 Part of Western by pass (Southern part including Bridge) Rajdeep Buildcon Pvt. Ltd.  May – 07 100.00 Completed
Package-IB
5 35/2569  Shivaji Nagar ROB to Nasratpur M/s Sharda Construction Aug-09 34.17 Feb-10
--------------
Sept-10
Package-II
6 10 / 3246 Mutha Chowk to Govardhan Ghat (With Bridge on Godavari) to Latur Road RKEC Projects Pvt. Ltd.  May – 07 70.00 May-08
--------------
Sept-10
Package-IIIA
10 11/278 Gurudwara Parikrama II R.K. Madhani & Co.  Jul-07 100.00 Completed
11 12/417 Baryamsingh Wine shop to Gurudwara Gate no. 2 to Yatri Niwas R.K. Madhani & Co.  Jul-07 100.00 Completed
12 13/667 Chikalwadi road to Bhgatsingh Road R.K. Madhani & Co.  July – 07 100.00 Completed in available land
13 14/600 Chikhalwadi road to bhagat singh road to crusher road. R.K. Madhani & Co. (Package-IIIA) Jul-07 100.00  Completed
14 15/156 Gurudwara Gate no 5 to bhagatsingh Road R.K. Madhani & Co. (Package-IIIA) July – 07 100.00 Completed
15 16/420 Gurudwara Gate No.4 to Gurudwara Road R.K. Madhani & Co.  Jul-07 100.00 Completed
16 17/719 Gurudwra Gate no 1 to Nagina Ghat R.K. Madhani & Co.  July – 07 86.00 Substantially Completed
17 18/238 Gandhi Statue to Mahaveer Chowk R.K. Madhani & Co.  July – 07 0.00 Road work not started because of noncompletion of sewer line
18 28A/663 Khalsa RUB Approaches R.K. Madhani & Co.  July – 07 100.00  Completed
Package-IVA
19 4/307 Keli Market to Barki Chowk M/s A.S.Construction Aug–09 17.56 April-10
--------------
Sept-10
20 5/769 Barki Chowk to Darbar Masjid Chowk to Nav  Ghat 0.7 April-10
--------------
Sept-10
21 27/797 Dr Savarikar Building to Navaghat 4.46 April-10
--------------
Sept-10
22 6/265 Darbar Masjid Chowk to Fort Yet to be Awarded 
23 22/380 Banda Ghat to Nagina Ghat INDU Projects Ltd  Jul-07 100.00 Completed
24 23/342 Vazirabad Road to Banda Ghat INDU Projects Ltd  Jul-07 100.00 Substantially Completed
25 26/342 Mahadev Dalmill to Gorakshan M/s Pooja Construction Jul-09 8.00 Jan-10
--------------              July-10
27 28/1399 Bafna Petrol Pump to Old Mondha to New Bridge on Godavari INDU Projects Ltd  Jul-07 100.00 Completed in available land
28 29/798 Crusher Road to Keli Market INDU Projects Ltd  July – 07 100.00  Completed
29 37/870 Shivaji Statue to Degloor Road INDU Projects Ltd  Jul-07 100.00 Completed
Package-V
32 24/2413 Degloor Road through CRC to Gyanmata School KETI Construction  May-07 100.00 Completed
33 32/3954 Airport (Forest Naka) to Chhatrapati Nagar KETI Construction  May – 07 100.00 Completed
34 39/2177 Anand Nagar Road to Naik College KETI Construction  May – 07 24.00 Work held up due to non completion of sewer Line
35 Text Box: 40A
Text Box: 40 B
Text Box: 40 C
Text Box: 40 B
40/2052
 Railway Station to  Yashwant college  KETI Construction  May – 07 100.00 Completed
Yashwant College to Baba Nagar 100.00 Completed
Baba Nagar to Bhagya Nagar 25.00 May-08
--------------
Dec-10
Package-VII A
36 19/375 Mahaveer Chowk to  Banda Ghat  M/s Sanman Construction Nov-09 100.00 Completed in Available Land
 
37 Tower/295 Beautification of Old Mondha M/s Ascent Construction Aug-08 100.00 Completed 

 

 

(Water Treatment Plant)

Weekly Work Progress Report 
construction of WTP ( Under JNNURM Project ) Nanded. Date : 30-05-2010
Sr. No. Location Capacity (ML) Last week progress Present progress of Execution Physical Achivement %
M/s. Pragati Construcion Co. Ltd. Chakur. Dist. Latur  North and South        
1 KabrabNagar (North Nanded) 35 MLD Completed & Commissioned on 27 th Feb 2010 100%
2 Asadwan  (South Nanded) 35 MLD Completed & Commissioned 100%

 

 

(STP & b SPS )

Weekly Work Progress Report
Construction of STP ( Under JNNURM Project ) Nanded. Date : 30-05-2010
Sr. No. Location Capacity (ML) State of Design Approval Present progress of Execution Physical Achivement %
  M/s. Sharda Construction Nanded.      
1 SPS N1 87 MLD Pipes for rising main received of 600 mm dia Excavation of SPS I at Node 30/51 completed 100% Further Excavation of SPs I in progress Rising main in progress Laid length 100 m DIK9 35%
2 SPS N2 Pipes for rising main received 600 mm dia DIK9, Punps and motors received. (i) Excavation of SPS II completed. (ii) Footing completed. (iii) Vertical wall in progress, (iv) Rising main completed except gap of 300 m for Railway Crossing For SPS II concrete work for vertical wall in progress and vertical wall completed. Laid length 70% DIK9
3 SPS N3 Pipes for Rising main received, Punps and motors received. Excavation of SPS III completed, PCC Completed Footing work and vertical wall is in progress. Rising main completed 90%
4 STP at North Nanded Design sanctioned for bunds etc. Excavation for ponds in progress also bunds also in progress. 50 % work of 3 ponds completed. Out two ponds of Anerobic, Aerobic and setting ponds one of each in completion stage.
M/s. Hydroair Techtonic (PCD) Ltd. Mumbai    for South 
2 SPS & STP @ Vasarni South Nanded 30 MLD G.A.of SPS Drawing submitted Work held up due to Land Acqusiation problem 80%

 

 

(Bridge & ROB )

Weekly Progress Report for Road Works
(For the week ending on 30 th May 2010) 
Sr. No. Name of the work Name of Contractor Date of Award Package Award Cost
( Rs in Lakhs)
Cummulative Progress  % Cummulative progress  Scheduled / Expected Completion
1 2 3 4 5 6 7 8
NAD-015              
1 Godavari River Bridge  RKEC Projects Pvt. Ltd. May – 07 4226  Work Completed 100.00% August-08
--------------
July-10
2 Railway Over Bridge RSVCPL & PV Rao (JV) Jul-07 2203 Completed & Opened for Traffic 100.00% July-08
----------------
Completed & Opened for Traffic

 

(ESRs )

Work Progress Report (Progress of work done upto date)  
construction of ESRs ( Under JNNURM Project ) Nanded.  
Sr.No. Location Capacity (ML) Staging Height (m) Work done upto last week Award Cost (Rs. In Laksh) Expenditure (Rs. In Laksh) Physical Progress % Financial Progress. %
M/s. Rudrani Construcion Co. Ltd. Aurangabad    North-West Nanded               
1 Stadium  2.5 20 Completed except misc & aliied works 537 479.79 Completed 89%
2 Workshop 1.9 19 Completed except misc & aliied works
3 Sunder Nagar 2 6 Completed except misc & aliied works
4 Nana Nani park 1 19 Completed except misc & aliied works
5 Sneh Nagar  ( Library) 1.65 18 Completed except misc & aliied works
6 Sneh Nagar (Yashwant Nagar) 2 17 Completed except misc / aliied works and hydrulic testing
M/s. Gleg Engineers Pvt. Ltd. Mumbai     North-East Nanded                  
7 Shakti Nagar 2.5 20 3rd stage columns are in progress 505 136.4 51% 27%
8 CRC Bondar 2.25 17.5 Further work of wall is in progress.
9 Trenching ground  1.25 20 Excavtion partly done. No further work
10 Nandigram Society 2.5 20 Staging completed further work stand still
11 Darwesh Nagar 1.25 20 Location site to be handed over by corporation
M/s. Gleg Engineers Pvt. Ltd. Mumbai     South  Nanded        
12 Kavtha  2.5 20 Structuraly completed except allied and misc. work & hydraulic testing 750 298.54 51% 40%
13 Asarjan 2 20 Bed casted, No further work
14 Vasarni 2 15 Excavation partly done. Unequal levelling excavated. Sway analysis submitted.PCC work in Progress
15 Asadwan MBR  2.5 19.4 Structully Completed. Hydrulic testing and allied work balance
16 Asadwan 2.0ML (S4)  2 20 Completed upto 2nd stage, further work stand still
17 Asadwan 2.5 ML (S6) (Near Latur Road)  2.5 15 Base slab casting completed.
18 Asadwan (S7) 1.5 10 Excavation partly done, no further work

 

 (Rehabilitation Work)

Weekly Work Progress Report (Progress of work done upto date)
Rehabilitation Work ( Under JNNURM Project ) Nanded. Date : 30-05-2010
Sr. No. Location Agency Name Detials Last week progress Present progress of Execution Physical Achivement % Remark
1 North Nanded M/s. Pragati Construction Co. Chakur. Civil work Kabranagar - CLF No. 2 reparing is in progress Kabranagar - CLF No. 2 reparing is in progress 98%  
Mechanical Kabranagar - Chlorination installation Work in Progress
2 South Nanded M/s. Allied Electro Pvt. Ltd. Mumbai Civil work Completed & Commissioned 100%  
Mechanical

 

 

 (Strom Water Drain Work)

Weekly Work Progress Report  
Storm Water Drain   Date : 30-05-2010
Sr No. Location Name of Contractor Date award / Comm date Award Cost (Rs. In Lakhs)  % Physical Progress
1 Package -I M/s Keti Construction 21-Aug-09 1785 25.00%
2 Package -II M/s M.T.Phad Construction 27-Aug-09 745 25.00%
3 Package -III M/s Sharda Construction 27-Aug-09 1757 26.00%