I.
Ongoing Project Development
Initiatives
NWCMC has already initiated
preparation of sectoral master plans and detailed project
reports across most sectors. NWCMC does not have the required
institutional capabilities for project planning and
development – they have engaged Infrastructure Leasing &
Financial Services Limited (IL&FS) as their Program Manager,
considering the scale and complexities involved in the
proposed developments. IL&FS is mandated to develop projects
and manage their implementation upto commissioning. IL&FS has
also committed in principle to fund NWCMC for its external
borrowing requirements.
Some of the key project
development initiatives underway under this engagement are
briefly described hereunder.
NWCMC is carrying out a
detailed master planning for the entire riverfront on either
banks of the River Godavari on either banks, within the city
limits. The focus of the master plan is to revive the River
Godavari in Nanded through water retention and interventions
aimed at enhancing the functional and scenic heritage of the
river. Special attention is being laid on the zoning plan, so
as to ensure reviving and conservation of the inner city
fabric in the core city area along the river banks. Other
interventions include development of ghats, public spaces,
gardens, eco parks, botanical garden, mela ground, stadium,
etc. on either bank. Figure 8 presents a preliminary concept option for
the riverfront development.
River MAP

Figure 9:
Glimpses of Proposed Riverfront Development Components



|
Sl. |
Milestone |
Date |
Remark |
|
1 |
Field Surveys |
18.06.2006 |
Completed |
|
2 |
Concept Plan Options |
15.06.2006 |
Completed |
|
3 |
Detailed Master Plan |
31.07.2006 |
Underway |
|
4 |
Detailed Engineering Report for
selected components |
15.10.2006 |
underway |
1.2.
Water Supply
The scope of work entails
improvements to the water supply system in Nanded. Specific
sub-project components being addressed include:
a.
For South Nanded
i.
Source creation and water treatment plant
ii.
Pumping machinery at source and at WTP
iii.
Transmission main
iv.
New service reservoirs within town
v.
Distribution system
vi.
Additional infrastructure for point loads
b.
For North Nanded
i.
Improvement & augmentation of source
ii.
Improvement & augmentation of WTP
iii.
Improvement & augmentation of pump sets at source (WTP)
iv.
Transmission main
v.
Additional service reservoirs (ELSR and/or GLSR)
vi.
Capacity addition of distribution system
vii.
Rehabilitation of distribution system (pipes & valves)
viii.
Rehabilitation of house service connections
1.2.1.
Project Development Timelines
|
Sl. |
Milestone |
Date |
Remark |
|
1 |
Master Plan for
Water Supply |
30.06.2006 |
Underway |
|
2 |
Detailed Engineering
Report for South Nanded |
|
|
|
|
Source creation
and Water Treatment Plant; Pumping Machinery at source and
at WTP; and Transmission main |
15.08.06 |
Underway |
|
|
New Service
Reservoirs within Town; and Distribution System |
31.07.06 |
Underway |
|
|
Additional
infrastructure for point loads |
15.08.06 |
Underway |
|
3 |
Detailed Engineering
Report for North Nanded |
|
Underway |
|
|
Improvement & Augmentation of Source;
and Additional service reservoirs (ELSR and/or GLSR) |
15.07.06 |
Underway |
|
|
Improvement & Augmentation of WTP; and
Improvement & Augmentation of Pump sets at source (WTP) |
31.07.06 |
Underway |
|
|
Transmission main; and Capacity
addition of Distribution System |
15.08.06 |
Underway |
|
|
Rehabilitation of Distribution System
(Pipes & Valves); and Rehabilitation of House Service
Connections |
15.09.06 |
Underway |
1.3.
Sewerage & Sanitation
The scope of work entails
improvements to the sewerage system in Nanded. Specific
sub-project components being addressed include:
a.
For South Nanded
i.
Collection System
ii.
Sewage Pumping Stations
iii.
Sewage Treatment Plant
b.
For North Nanded
i.
Improvement & Augmentation of the existing system –
collection, pumping and treatment systems
ii.
Extension of the collection system to uncovered areas
1.3.1.
Project Development Timelines
|
Sl. |
Milestone |
Date |
Remark |
|
1 |
Master Plan for
Sewerage System |
30.06.2006 |
Underway |
|
2 |
Detailed Engineering
Report for South Nanded |
|
|
|
|
Collection system
for Priority Zone |
31.07.06 |
Underway |
|
|
Collection system
for Other Zones |
31.08.06 |
Underway |
|
|
Sewage Pumping Station; and Sewage
Treatment plant |
15.09.06 |
Underway |
|
3 |
Detailed Engineering
Report for North Nanded |
|
Underway |
|
|
Condition assessment of existing system |
15.07.06 |
Underway |
|
|
Collection system |
15.08.06 |
Underway |
|
|
Improvement & Augmentation of pumping
stations; and Improvement & Augmentation of Sewage Treatment
Plant |
15.09.06 |
Underway |
The project entails design and
development of a storm water management and drainage system
Nanded. There are about 26 major nallahs that drain the city’s
storm water into the river. The plan is to assess the capacity
of these nallahs and the tertiary storm water network to
effectively drain out all surface runoff, and to ensure minimal
flooding.
|
Sl. |
Milestone |
Date |
Remark |
|
1 |
Master Plan for
Storm Water Drainage |
30.06.2006 |
|
|
2 |
Detailed Engineering
Report for Storm Water Drainage |
15.10.2006 |
|
1.5.
Transportation Infrastructure
The scope of work for project
preparation for transport infrastructure is focused on
strengthening, widening and beautification of existing arterial
roads. The widening proposal is based on the proposed
Development Plan widths. There are about 40 such priority roads
measuring about 60 km. In addition detailed project reports are
being prepared for three RoBs and one major bridge across the
River Godavari. These proposed interventions are critical from
the point of view of the Gur ta Gaddi Tercentenary celebrations’
circulation requirements as also in the context of city-wide
transportation network. The detailed project reports for these
components will be finalized by August
31,
2006.
View Figure
10: Priority Roads for the Gur ta Gaddi Tercentenary
Celebrations
|