|
Nanded city has an underground
sewerage system that was designed and developed by MJP in
1969-71. The sewerage system was handed over to the then Nanded
Municipal Council in 1974 for routine operation and maintenance.
The sewerage system was designed for a peak load of 10 MLD. The
sewerage system has been mal-functioning for several years, with
the 9 MLD treatment plant at Bondar virtually non-functional.
There is another sewage treatment plant near CIDCO township in
south Nanded, with a treating capacity of 6 MLD.

The total length of the sewerage
system is about 425 km, comprising about 25 km of main sewers
and about 400 km of laterals. While this may indicate adequate
reach of the system compared to the total road length of about
425 km in the city, the fact is that only the core city area
between the railway line and the river Godavari is adequately
covered, while the rest of the area in North Nanded is
inadequately covered.
There are two pumping stations –
one at Old Mondha, near Gayatri Mandir (4 MLD) and another at
Choufala Sul Tekdi (9 MLD).
Table 14
presents a summary of the sewage collection system in Nanded.
Table 14: Summary of the Sewage Collection System in Nanded
|
Diameter
(Inches) |
Sewer Line / Hierarchy |
Length
(Km) |
|
9 to 36 |
|
007.00 |
|
9 to 42 |
“B” type
Sewer Trunk Line |
010.00 |
|
9 to 24 |
“C” type
Sewer Trunk Line |
004.00 |
|
6 to 24 |
“D” type
Sewer Trunk Line |
002.00 |
|
6 to 24 |
“E” type
Sewer Trunk Line |
002.00 |
|
6 to 24 |
Brach
Lines / Laterals |
400.00 |
|
Total Length |
|
425.00 |
There are four trunk sewers serving the city which are
designated as A, B, C, D and E, besides smaller branch sewers.
Major issues related to sewerage system relate to A, B & C sewer
and there is a major bottleneck point near Vidyut Bhavan where
three sewers meet and lead to the B sewer enroute.

a.
B Sewer: This is the largest sewer (42” dia) for the town
and it serves the most thickly populated area of Nanded.
Majority of sewage generated flows through this sewer. The
chronic stretch of this sewer is from Bafna Junction up to the
Chand Masjid area. Most of this stretch is built upon by slums
encroached upon it. Thus the stretch of almost 1.4 Km is
rendered inaccessible even for routine maintenance. This has led
to severe silting inside the barrel of the sewer and the
manholes blocking it completely in larger part of this stretch.
The staff of NWMC has informed many collapses in this stretch in
recent past. Complete blocking has resulted in the STP getting
scanty sewage and it appears that the sewage from the line is
percolating the ground - which is black cotton for a depth
exceeding 8 to 10 m below GL and thus polluting the ground and
ground water, which is available at substantially higher depths.
b.
C Sewer: This 36” dia sewer passes through the Veterinary
college area in front of MAFCO compound. By the time the sewer
enters the veterinary college it is heavily encroached upon by
slums. Many crown collapses have been reported in this area by
the NWMC staff. Fortunately, the collapses have not been below
the hutments else it could have been disastrous. It is also
noted that the fine grained soil – black cotton is eroding and
entering in to the pipeline through openings thereby resulting
in loss of ground support to the pipeline and this in turn is
causing joint settlement and severe misalignment.
c.
A Sewer: This is a smaller sewer, which is showing
blockages and resulting in inefficient functioning.
The overall sewerage network is
over 35 years old and is in a very bad condition. The
foundation of the pipeline is highly dilapidated, resulting in
cracks ion the RCC sewer mains. Due to the predominantly black
cotton soil in Nanded and ageing of the sewerage system
components, the chambers and the manholes have also developed
cracks. In addition, due to inadequate capacity, choking and
substantial breaches in the system, the sewage discharged into
the system does not flow as per plan. Most of the sewerage and
storm water drainage system are now intermingled and they
ultimately discharge untreated sewage mixed with sullage and
storm water into the river Godavari.
There are about 23,120 sewer connections (toilet seats connected
to the sewerage system), constituting only about 36 per cent of
the total number of property tax assessments.
View PDF Figure 6: Map showing key Components of the Sewerage
System
NWCMC has set up 41 public
convenience units at strategic public locations and in slum
areas to provide safe and hygienic sanitation facilities to the
floating population as well as to slum dwellers. Such public
conveniences are located at 33 different locations, offering
about 323sets.
NWCMC had received assistance of
about Rs. 13 crore under the National River Action Plan from the
Government of India, to undertake works to prevent pollution of
Godavari river. The project components include:

a.
Interception & diversion of sewage (Rs. 9.95 crore)
i.
Extension of Osmanshahi Nallah and construction of a 30 m
long weir
ii.
Construction of interception weirs across 19 drains
iii.
Improvements to connecting and branch sewers
iv.
Construction of interceptor sewer from MH to pumping
station (4 km and 52 manhole chambers)
v.
Construction of pumping station with transformer yard
generator room
vi.
Construction of 1.75 km of pumping main
vii.
Construction of approach bridge
viii.
Installation of pumping machinery and transmission main
ix.
Miscellaneous works (fencing, electrification, etc.)
b.
Sewage Treatment Plant (Rs. 2.77 crore)

a.
The sewerage system in Nanded comprises about 425 km of
sewer network confined to north Nanded. However the system is
virtually non-functional due to choking and breaches throughout
the system.
b.
The treatment plant designed for a peak load of 10 MLD is
far below the estimated 40 MLD of sewage generated – it is
non-functional though.
c.
Over time, in order to ensure discharge of sewage, the
sewerage system has been intermingled with the storm water
drainage network and all the sewage, sullage and storm water are
discharged into the Godavari river.
d.
Slum sanitation has not been a conscious priority and
public conveniences have not been strategically provided.
e.
NWCMC is currently carrying out a detailed engineering
study to improve the sewerage system in the city. This study
seems to be ignoring the existing system of about 425 km of
sewer network, and is proposing a new system, while an effort
needs to be made to integrate as much of the existing system as
possible.
a.
NWCMC should carry out a diagnosis of the sewerage
existing system and propose a new system integrating as much of
the existing system as possible. The sewerage plan should focus
on the densely populated areas and potential development areas,
while the fringe and under-developed areas need to be serviced
through decentralized low cost sanitation methods in a manner
that they can be incorporated in the mainstream system as and
when the achieve threshold sewage flows required for efficient
functioning of the sewerage system.
b.
A detailed slum sanitation program needs to developed and
implemented.
c.
A comprehensive operations manual needs to be prepared
and the municipal staff to be trained in operating the system in
a scientific manner.
2.
Storm Water Drainage

The storm water drainage system (SWD)
in Nanded comprises of about 261 km of roadside drainage network
of different hierarchies and types, as presented in the
following table. In addition, there are about 12.5 km of
nallahs that drain into the river Godavari. The SWD system is
intermingled with the sewerage system and comprises the natural
drainage system and the road side man-made drainage network.
Table 15 presents a summary of the storm water
drainage network in Nanded.
Table 15: Summary of Storm Water Drainage Network in Nanded
|
Sl. |
Type of Drains |
Length (Km) |
|
1 |
RCC Drains |
38.29 |
|
2 |
CRS Drains |
106.13 |
|
3 |
PCC Drains |
37.34 |
|
4 |
Kaccha
Drains |
51.68 |
|
5 |
Brick Drains |
0.32 |
|
6 |
Others |
27.00 |
|
|
Total Length |
260.75 |
The city, specifically the core old city area is prone to
frequent floods, as the low and high flood lines extend into the
heart of the area. There are other areas in North Nanded beyond
the railway line and in South Nanded on the banks of the river
Godavari, that are prone to flooding during the monsoons due to
an inadequate storm water drainage network.
The storm water drainage network
is unplanned and mainly comprises roadside drains primarily
intended to drain the road surface. Substantial portions of the
city along the riverbank on both sides and areas north of the
railway line are prone to flooding and water stagnation in
monsoons, resulting in loss to economy and health hazards.
NWCMC needs to develop an
adequate storm water drainage network in a scientific manner,
taking into consideration key parameters of precipitation
intensity, catchments delineation, percolation characteristics
and surface runoff. The possibility of rainwater harvesting at
the micro and macro levels needs to be explored and implemented.
The total amount of solid waste
generated in Nanded is to the tune of about 149 tonnes per day,
at an average of about 300 gpcd.

While there has been no
initiative to establish the waste characteristics, source-wise,
about 73 percent of the quantity of waste is estimated to be
generated from domestic sources, followed by about 23 percent
from commercial establishments and markets and the rest from
industries.
The city is divided into five
zones for the purpose of conservancy operations – street
sweeping and collection. There are 530 uncovered dustbins and
10 containers placed all over the city for collection of
municipal solid waste. The corporation has about 20 vehicles of
different types, for conservancy purposes, but most of these are
non-functional and prone to frequent breakdown. These vehicles
are primarily used to service far-flung areas like the CIDCO
Township and other fringe areas.
Most of the collection and
transportation activities are outsourced to a private contractor
who is paid at the rate of Rs. 60,000 per day for collection and
transportation of solid waste from all the zones. The Municipal
Corporation’s role is now largely confined to street sweeping
and monitoring collection and transportation activities of the
private Contractor.
The private contractor has
deployed 20 hydraulic tractors, 2 covered waste collection vans,
1 dumper placer, and 150 Cycle rickshaws for door to door
collection of dry and wet waste in separate containers.
There has been no attempt to
measure / audit the waste collection system, but crude estimates
are that the collection efficiency is to the tune of about 75
percent of the waste generated.
Presently the Municipal Solid
Waste is disposed in a dumping ground at Valmiki Nagar, near
Maltekdi in an area of 3.32 Ha. There is no treatment facility,
and the garbage collected from the city is merely dumped at this
site. This site has been in use since around 1975 and may need
to be assessed for its capacity to handle more dumping, as well
as to assess its suitability for installing scientific treatment
and disposal methods.
The Municipal Corporation has
sought to acquire a piece of land measuring about 7.20 Ha at
Puvani, for development of a scientific engineered landfill
facility.
There are no estimates of the
quantum of bio medical waste generated in Nanded. NWCMC has
engaged a private agency for the collection of biomedical waste
from all the medical facilities in the city. This agency
collects biomedical waste from all the private facilities for a
monthly fee of Rs. 300 per private clinic, and transports it to
the Incinerator facility at the General Hospital for disposal.
The private agency pays a fee per unit weight of waste to be
disposed at the Incinerator. It is estimated that about 300 kg
of bio medical waste is generated per day.
The waste collection efficiency
is to the tune of only about 75 percent of the daily waste
generated. The Corporation does not employ any scientific
method for treatment and disposal of solid waste. The current
disposal site was intended to be developed as a
recycling-cum-disposal facility with a compost plant, but it
didn’t work out due to heterogeneous characteristics of the
waste, with substantial quantities of plastic and construction
debris.
There is a need to develop a
comprehensive solid waste management system in the city based on
adequate investigations and estimation of quality and quantity
of waste generated. The proposed system should aim at applying
best practices solid waste management, including in waste
segregation at source, community-based collection systems,
efficient transportation and scientific treatment and disposal
of waste. There are several models of privatization being
practices in the country today – NWCMC could consider adopting
most appropriate frameworks, methods and technologies for
managing its waste. |